HEAVY
DUTY FLOOR TOPPING
This application brochure is intended to assist the contractor in
successfully installing the following products manufactured by ChemProof
Polymer Flooring.
PERMACOAT 3000, 4000, 5000
PERMACOAT 3000 CT
PERMACOAT 2000
GENERAL
DESCRIPTION
The PERMACOAT systems are 100% solids epoxy and 100% solids modified
epoxy floor coatings. They can be utilized as a glaze coat for the
PERMATEC high build floors, or as a two coat flooring or containment
system (16-60 mils). When applied as a two coat floor or containment
systems, a silica broadcast is required between coats.
PERMACOAT systems can be
installed over most sound floors, including old or new concrete, steel
and wood.
All of the PERMACOAT systems
are applied in the same manner, only the "A" to "B"
(Resin to Hardener) weights and ratios are different. For a complete
ratio listing refer to the "Weights and Ratios" bulletin.
PACKAGING
Each kit size is made up of the following components:
Part A - Resin
Part B - Hardener
| Gallon
Kit |
Component |
Package |
|
|
1 |
A |
1 - 1
gal. pail |
|
|
|
B |
1 - 1 qt.
can or 1/2 gal. jug |
|
|
3 |
A |
1 - 3 1/2
gal.
pail |
|
|
|
B |
1 - 1
gal. or 2 1/2
gal. jug |
|
Silica is not normally supplied with PERMACOAT products
due to the shipping costs. A cleaned, dried, rounded silica is
recommended. Mesh sizes of 30-75 are most commonly used, with the size
being determined by the final texture desired.
Note: Do not use mesh sizes over 75 unless a sample
areas has been performed. Silica over 75 mesh may cause uneven finishes.
SURFACE
PREPARATION
New Concrete - The concrete should be well cured for a minimum of
twenty-eight (28) days, per ACI 308-81, (R-1986), clean, dust free and free of all
contaminants. Mechanical methods such as sandblasting, or
shot blasting should be employed to remove the weak layer of surface
laitance. A minimum tensile strength of 200 psi is required of the
prepared surface. Acid etching with muriatic acid is acceptable but less
desirable. Care must be taken to completely remove all residual acid
prior to the application of any coating product.
CHECKING FOR
CONTAMINATES IN NEW AND EXISTING CONCRETES
Prior to commencing the surface preparation in new or existing concrete,
all surface contaminates such as chemical residue, waxes, oils, grease,
paints, or sealers must be removed.
Paints or sealers can be removed by
mechanical means, such as shot or sand blasting. Mechanical methods may
not be adequate for the removal of chemical residue, waxes, oils and
grease.
If greases and oils are present,
degreasing preparations must proceed the final concrete prep. After
scrubbing the concrete with a degreasing solution, a 1 to 1 mix of
muriatic acid and water should be poured onto the substrate. If a
vigorous and uniform bubbling appears, the degreasing operation was a
success and normal preparation procedures may begin. If the bubbling
does not appear, the degreasing step must be repeated.
COVERAGE
The table below gives finished floor thicknesses after the silica
broadcast (40 mesh) and the final topcoat. Only the thickness of the
first coat is varied.
| 1st
Coat Coverage |
1st
Coat Thickness |
Finish
Floor Thickness |
|
| (Sq.
Ft.) |
(mils) |
(mils) |
| 200 |
8 |
25-35 |
| 150 |
12 |
30-40 |
| 100 |
16 |
50-60 |
Note: The second coat, or
topcoat for the systems listed above will totally encapsulate the
exposed silica at a coverage rate of approx. 100 sq. ft. per gallon.
MIXER
REQUIREMENTS
A jiffler mixer on a low
speed (400-600 rpm) drill has proven to be most effective in mixing
PERMACOAT products. When mixing 3 gallon kits, the larger jiffler mixer
should be used.
MIXING
Prior to application, the PERMACOAT material (Resin & Hardener) and the substrate should be a minimum of 65 degrees F.
Do not begin mixing until
material is ready for use.
-
Premix the Part "A" for 30 seconds to
assure even pigment distribution.
-
Pour Part "A"
(Resin) and Part "B" (Hardener) into the mixing bucket,
mix for approximately 1 1/2 - 3 minutes.
-
Immediately remove the
mixed material and distribute it onto the work areas. The prompt placement
of the material will insure adequate time for the application.
Do not mix more than 3
gallons at one time.
APPLICATION
Note: Before applying PERMACOAT products, the substrate (i.e. Concrete
or a PERMATEC floor) should be visibly dry.
PERMACOAT
AS A GLAZE COAT (over PERMATEC Heavy Duty System)
After mixing immediately pour the PERMACOAT material onto the floor.
Using a rubber squeegee (or steel trowel), pull the material tightly and
evenly over the desired area (Typically 90-110 sq. ft. per gallon).
Follow behind the squeegee with a quality mohair or wool nap roller to
distribute the resin evenly and encapsulate all the exposed silica.
PERMACOAT
AS A FLOOR OR CONTAINMENT SYSTEM
After mixing immediately pour the PERMACOAT material onto the floor.
Using a rubber squeegee (or steel trowel), pull the material tightly and
evenly over the desired area (Typically 100-200 sq. ft. per gallon).
Follow behind the squeegee with a quality mohair or wool nap roller to
distribute the resin evenly.
A silica broadcast should be
made approx. 10-20 minutes after the area has been back rolled.
The excess silica can be
removed as soon as the PERMACOAT will support foot traffic (Approx. 4 to
8 hours @ 70 degrees F). Following the removal of all excess silica, the
second coat of PERMACOAT is applied with squeegees and rollers as set
out above. There is no silica broadcast into the final coat. The final
coat should be applied within 48 hours of the first to insure a proper
bond.
BROADCASTING
Silica broadcasting should not begin until the application
process (i.e. back rolling) has progressed for
approx. 10-20 minutes. Silica can be broadcast by hand and in larger
applications can be blown with a 3-bag pressure pot. Broadcast until
there is an even excess layer of silica and no "shiny" spots.
Note: Do not broadcast into
the working edge of the material. This will make it very difficult to
tie the next batch of material in properly. Also, allow the silica to
float down onto the resin surface as opposed to "sidearming"
the silica. This can cause the resin surface to be pushed into ridges.
CLEAN
UP
All mixing and application equipment should be cleaned immediately after
use. If this is done, soap and water, or biodegradable cleaners can be
used. If the material has begun to set, more aggressive solvents may be
necessary. Before using solvents, refer to their respective MSDS for
handling considerations.
STORAGE
AND SHELF LIFE
The PERMACOAT products should be stored at 50-90 degrees F and out of
sunlight. Containers should remain unopened until ready for use. If
stored as set out above, a minimum shelf life of 1 year can be realized.
WHERE
PERMACOAT PRODUCTS SHOULD NOT BE INSTALLED
PERMACOAT products should not be applied over substrates:
-
subject to hydrostatic
pressure
-
unsound structures
-
contaminated substrates
which cannot be cleaned
-
at temperatures below 65
degrees F (Consult ChemProof Polymers).
SAFETY
PERMACOAT flooring systems contain blended Epoxies as the resin and
blended Amines as the hardener. Protective clothing and gloves are
recommended to prevent sensitization to these materials. In case of
ingestion or eye contact, contact a physician immediately. MSDS are
available for this product upon request.